Off-plan delay is the most common property fight in Dubai and Abu Dhabi after a boom cycle. The buyer has paid. The tower is a slab. The sales office has a new completion date and a smile. The file is the sale and purchase agreement, the escrow or progress record, and the notices — not the mood board.
This article is general information for purchasers and investors. Real-estate counsel should read the SPA and the regulator extract before anyone stops cheques. Wider context: real estate disputes.
Read the date that is actually binding
- The completion or handover date in the SPA, including any permitted extension.
- Whether the developer registered a variation with the competent land department or municipality.
- Your payment schedule and whether you are yourself in arrears.
- Snagging, occupancy, and what “handover” means in that contract (keys, title, or a construction milestone).
A marketing leaflet that said 2024 does not override a clause that said 2026 plus force majeure. Force majeure is also not a blank cheque. It has to fit the clause and the facts.
Remedies buyers actually use
- Complete and claim. Take the unit, reserve rights, claim delay compensation where the contract or the rules allow it.
- Terminate and recover. Where the delay and the SPA support rescission, through the competent committee or court, with the escrow path in mind.
- Negotiate. A written variation: new date, waived fees, extras, or a payment pause. Get it on the developer’s letterhead and, where the project is registered, reflected in the system.
Public posts, group-chat petitions, and a threat to “go to the newspapers” are not a legal strategy. They can become a defamation problem.
Do not do this
- Stop instalments without advice.
- Sign a handover form that waives delay claims because you wanted the keys that afternoon.
- Pay cash to a “coordinator” to speed the title.
- Ignore a termination notice from the developer while you are yourself late.
Send Mohamed Alhamed the SPA, the payment receipts, and the last official completion notice. The first question is which date the system recognises — not which date the agent remember.